Polskie Elektrownie Jądrowe submitted an application for a construction permit for Early Works at the nuclear power facility

30.10.2026

On 30 October, Polskie Elektrownie Jądrowe (PEJ) submitted an application to the Head of the Pomorskie Voivodeship for a construction permit covering Early Works for part of the works related to the construction of Poland’s first nuclear power plant. The Early Works project involves preparing the site for the construction of the nuclear power plant and the necessary infrastructure, including the onshore part of the facility’s cooling channels. These are works that, in accordance with applicable regulations, may be carried out without a separate license from the President of the National Atomic Energy Agency (PAA).

This phase will include earthworks preparing the site where three AP1000 reactors will be built in the future. The works will cover, among other things, the excavation of deep trenches, the stabilization of their walls, and the implementation of measures to protect the trenches from groundwater inflow.

The construction of the nuclear power plant is the largest energy project in the history of Poland. We have amended the regulations to streamline the project delivery. The application for the permit for Early Works is a practical use of these solutions. Nuclear power means greater energy security for our country and a stable energy supply for decades to come for the Polish economy and Polish households.

The application for Early Works is crucial for at least two reasons. Firstly, from a scheduling perspective, it allows us to begin some of the basic work, which is not directly related to the nuclear part of the power plant, earlier, without having to wait for further administrative approvals, while maintaining the highest standards of quality and safety. Secondly, submitting this application would not have been possible without cooperation with the government and the efficient processing of the necessary amendments to the Nuclear Special Act, which is why I would like to express my sincere gratitude to all the institutions and parties involved in this process"

The Early Works project also covers the construction of a retention basin to collect rainwater and meltwater, as well as the construction of internal roads and special launch pits for the Tunnel Boring Machine (TBM).

 

The scope of work also includes the construction of the onshore part of the Circulating Water System (pipelines for the intake and discharge of water used to cool down the power plant). Previously, this system had been classified by the President of the National Atomic Energy Agency as not safety-related. Consequently, it can be built as part of Early Works for the “non-nuclear” part even before the licenses required for the power plant’s main facilities are obtained. According to the plans, the cooling system pipelines – that is, the seawater intake and discharge channels – will be installed beneath the beach and the seabed of the Baltic Sea using a trenchless method.

 

Early Works are designed to prepare the site and build the necessary infrastructure. Their goal is to create conditions necessary to begin the actual construction of the nuclear power plant in the subsequent phases of the project.

 

The mechanism of Early Works was introduced into the Polish legal system by the Act of 3 July 2026 amending the Act on the preparation and execution of investment projects in nuclear power facilities and associated investment projects, as well as certain other acts. The purpose of the amendment was to streamline the construction of nuclear power facilities, including Poland’s first nuclear power plant, by allowing certain construction activities to be carried out prior to the main phase of the project.

 

Poland’s first nuclear power plant is being delivered in Pomerania in the Choczewo commune. The plant, with an installed capacity of 3,750 MWe, will feature three AP1000 reactors from the U.S. company Westinghouse. Currently, the second phase of preparatory works is underway at the “Lubiatowo-Kopalino” site, which involves preparing the infrastructure for the future construction site. The contractor, Bechtel, is also conducting in-depth onshore and offshore geological surveys. The investor, PEJ, is continuing its efforts to obtain further administrative decisions, including preparations to submit an application for a construction permit in 2027.

 

 

 

 